20 men take 10 days to complete a piece of work. find the time taken by 8 men to complete the same piece of work

Respuesta :

michaelpuen12 michaelpuen12
  • 14-06-2021
For the 8 men to finish the work it would take 16.76 days to finish the piece of work
Answer Link

Otras preguntas

what is the volume in m³ of a cubic tank if the edge is x+3 m​
In your own words.... What is a non-profit organization? What is an example of one?
What Was Ancient Civilization in Egypt Like?:Question 1 Which of these geographic factors contributed to the success of ancient Egyptian civilization? Select on
Pleasee helpp, I’m so confused, I will mark brainiliest and pleasee don’t use links
The masses of the oranges on sale at a farm stand are normally distributed with a mean of 239 grams and a standard deviation of 25 grams. Enter the Z-score of a
Match the vocabulary words Spanish to English
307 grams of NaHCO3 (MM = 84 g/ mol) are dissolved in 781 of water what is the molarity of the solution? (Multi-step)
Write a function nexthour that receives one integer argument, which is an hour of the day, and returns the next hour. This assumes a 12-hour clock; so, for exam
find the circumference of the pizza to the nearest tenth (10in)
Who ever is reading this: I love u. U matter. The world needs u hang in there ik it may be bad but u deserve the world <3 ur beautiful no matter ur shape, si