contestada

It takes 6 workers 8 hours to tile a hall . How long will it take 4 workers to complete the same job

Respuesta :

icandoitjwk icandoitjwk
  • 15-01-2022
6w=8
2w=8/3

So
4w=8/3x2
4w=16/3
Answer Link

Otras preguntas

Olivia said her pencils is 14.0 cm long. how do you know she measured to the nearest millimetre?
Explain why a chlorinated swimming pool water would be a homogenous mixture?
create a humorous" elf school rules"
The three reasons Americans were ready to go to war with England were.....
a number increased by 4 is the same as 19 minus 2 time the number
Witch is a primary way an archaeologist would decide where a tample stood A. evaluating clues on clay tablets B. reading about the remains of an ancient s
Why did southern whites feel threatened by the Missouri Compromise?
What was Manchukuo? a. part of the Dutch East Indies b. a town along the Burma Road c. puppet state after Manchuria d. an important Japanese city
why is freezing water extremely biologicallyrelevant
what were the political contributions of Thomas Jefferson and Richard Henry Lee